1.1.4 Fabrication

ProcessSenderReceiver
31-60 00 00 Implementation Phase34-35 15 11 Contractor34-35 10 14 Fabricator

Different structural systems and materials impose their own information requirements and workflows. These have been identified by the Precast Concrete Institute (PCI), American Institute of Steel Construction (AISC), and the American Concrete Institute (ACI).

For fabrication of structural steel and miscellaneous steel (such as for railings), elements contained within a bridge model and their connectivity may be used by a fabricator to elaborate, however typically do not carry sufficient detail to be directly used by CNC machines for automated production. The most common data format in use for this detail is DSTV, commonly having a file extension of "NC1". Information captured for steel fabrication may include:

NOTE  This exchange currently provides minimal information to be useful for the downstream Design Plans exchange; it is anticipated to be elaborated in a future extension.

  Fabrication
Entity/ConceptAttributesConstraintsIE
IfcBeam
  Structural Curve AssignmentReferencedByRR
  Annotation 2D GeometryRepresentation
IdentifierTypeItemsDescription
  IfcTextLiteralWithExtentPiece marks.
  IfcCartesianPointPop marks.
  IfcIndexedPolyCurveContour marks.
OO
  Element PositioningPositionedFrom
PlacementTransformDescription
VERTICALWARPBridge girders are positioned and transformed to follow the alignment curve.
VERTICALPLACEBridge cap beams and diaphragms are positioned without transformation.
OO
IfcCostItem
  Object NestingIsNestedBy
Type
IfcCostItem
OO
  Control AssignmentControls
TypeDescription
IfcElementElements assigned to quantity line item.
RR
IfcCostSchedule
  Object NestingIsNestedBy
TypeDescription
IfcCostItemEach quantity line item is nested directly under the cost schedule in order.
RR
IfcMember
  Element NestingIsNestedBy
TypePredefinedType
IfcMember 
OO
  Surface ConnectivityConnectedFrom
Type
IfcPlate
RR
IfcPlate
  Surface ConnectivityConnectedFrom
TypeDescription
IfcBeamPlates may be attached to beams, functioning as stiffeners or gusset plates.
RR
  Body SweptSolid Extruded Arbitrary GeometryRepresentationOO
  Annotation 2D GeometryRepresentation
IdentifierTypeItemsDescription
  IfcTextLiteralWithExtentPiece marks.
  IfcCartesianPointPop marks.
  IfcIndexedPolyCurveContour marks.
OO
  Element NestingIsNestedBy
TypePredefinedType
IfcPlate 
RR
IfcPlateType
  Type Body SweptSolid Extruded Arbitrary GeometryRepresentationMapsOO
  Type Body SweptSolid Extruded Arbitrary Void GeometryRepresentationMapsOO
IfcProject
  Project DeclarationDeclares
Phase
ObjectType
LongName
TypeDescription
IfcProjectLibraryReferenced projects incorporated into this project.
IfcTypeObjectType definitions defined by this project.
IfcActorActors participating in this project.
IfcCostScheduleQuantity takeoff schedules.
IfcTaskStages of bridge construction, assigned to corresponding girder framing.
IfcStructuralAnalysisModelStructural analysis model with sufficient detail to describe load combinations and results for camber ordinates, but not necessarily full result details.
IfcDistributionSystemDistribution systems for drainage or electrical conduit
RR
  Project UnitsUnitsInContext
Phase
ObjectType
LongName
DerivedUnitTypeDescription
Length unit as meters, millimeters, or inches.
RR
  Project Representation ContextRepresentationContexts
Phase
ObjectType
LongName
ContextIdentifierContextTypeDescription
Model3DContext for all 3D geometry.
Plan2DContext for all 2D annotations.
RR
IfcProjectOrder
  AggregationPredefinedType
IsDecomposedBy
Decomposes
PredefinedTypeRelatedObjectsDescription
 IfcCostSchedule A cost schedule may indicate costs and quantities where the cost schedule type may designate whether rates and/or quantities are estimated or final. Such cost schedule may have assigned cost items indicating detail, where each cost item may have assigned products, processes, or resources.
WORKORDERIfcWorkScheduleA work schedule may indicate tasks and scheduled times where the work schedule type may designate whether tasks and/or times are planned or actual. Such work schedule may have assigned tasks indicating detail, where tasks may be assigned to products and may have assigned resources.
RR
IfcRoot
  Object OwnershipOwnerHistoryOO
IfcSlab
  Element PositioningPositionedFrom
PlacementTransformDescription
VERTICALWARPBridge decks are positioned and transformed to follow the alignment curve.
OO
IfcWorkSchedule
  Control AssignmentControls
Type
IfcTask
OO